Today was the first day with a small crew from the contractor. It was apparent early on that there is a reason they do this professionally. After a 10 hour shift, with a small lunch break, they demolished an entire floor and some of another. For perspective, my nephew and I finished the basement demo that has been going on for five days. Granted, the basement is more involved but as you can see from the pictures, they don't mess around.After tomorrow, I expect to have most if not all of the demolition completed. Not bad for only owning the house for six days.
We received the first drawings from the architect last night and are having him make some changes due to a couple of errors. They should be finalized tomorrow which means we can get the construction permits and get the real party started. That also means we get to pick out cabinets. I'm sure that will a simple task.........
The HVAC is scheduled to be installed at the beginning of next week and I believe that will be at the same time that framing will be in full swing. All in all, a great start to the week. I hope it all goes this smoothly. (Commencing the biting of the tongue)


great progress! Basement looks great. Where did the green walls come from in the LR?. Love watching this :)
ReplyDeleteGreen walls are in the master bedroom and are a result of green paint on two layers of wallpaper which was under white painted wood paneling. Ta Dah!
ReplyDelete